Cape Coral's Notices to Industry: The 2026 Advisories That Change What You Can Build
Cape Coral's Building Division writes to builders directly. Not through the Land Development Code, not through the Florida Building Code, and not through anything a homeowner would ever think to search. It publishes short documents called Notices to Industry and Advisory Notices — a page or two each, usually dated, sometimes signed by the Building Official — and they are the earliest written warning that something about your house has changed.
They are also close to invisible. They live in a document folder under the Development Services pages, they are not announced, they are not indexed anywhere useful, and most of them never make the news. A client who reads every page of the code and every FAQ on the City's website can still miss the one notice that decides whether the shower in their master bath passes inspection.
Below are four from 2026, quoted from the City's own paper, each with its printed title and its printed date. Three of them change what you can build. One changes how you book the inspection that proves it. We have read each document in full and we say where each one stops short.
Where the series lives, and why you will not find it by searching
The notices are published at a stable path on the City's own domain, under Departments, Development Services, Notice to Industry. Each year has its own group, and when we read the index on November 23, 2026 the 2026 group held seventeen documents. The older groups go back years.
Two things about that collection matter more than its size.
First, the documents are dated. Most carry a printed issue date, an effective date, or both, and several are signed by name. In a market where almost every published answer about permitting is undated, a dated and signed page from the authority that issues the permit is the best evidence available short of the code itself.
Second, the documents are not uniform. Some are headed NOTICE TO INDUSTRY and some ADVISORY NOTICE, the two appear to be used interchangeably, and the file name does not always match what the document calls itself or the date printed inside it. Several carry the line “subject to change without notice.” None of them is the code. They are the City telling you how it intends to apply the code.
So a notice is not a rule you can cite back at anyone. It is a very good indication of what the plans examiner and the inspector are going to do, which for anyone actually building is the more useful of the two.
“Clarification on the Elevation Requirements for Recessed Shower Floors”
Advisory Notice, printed date November 12, 2026. Issued by the Building Division; no individual is named on it.
This is the one to read first if you are designing a house in a Cape Coral flood zone, because it closes a gap that a lot of high-end bathroom design walks straight into.
A curbless shower — no lip, no step, tile running flat out of the room and into the shower — is one of the most requested details in a modern custom house. The way it is usually built, the shower floor is recessed slightly below the surrounding finished floor so the water runs the right way. The notice addresses exactly that, and its answer is no.
The City says it reviewed ASCE 24-14, the Florida Building Code, the City's own Land Development Code, and held discussions with FEMA, and concluded: “There is no provision within the Florida Building Code or the referenced standards that exempt recessed shower floors” from the Base Flood Elevation plus one foot requirement when the Lowest Floor Elevation is determined.
The operative sentence is the second one. A recessed shower floor “is still considered part of the finished floor system and must be elevated to at least BFE + 1 foot”. And in case the first two leave room: “Recessing the shower floor does not create an exemption from the applicable flood elevation requirements.”
The consequence is printed plainly. “Construction that does not comply with this requirement will not be approved or pass the applicable reviews and inspection.” The notice says plan review and inspections will both account for recessed shower floors when checking Lowest Floor Elevation compliance, and that the requirement applies to new construction and to substantial improvements in designated floodplain areas.
The word substantial improvement is doing real work in that sentence, and it is the hinge of a separate and much larger set of rules — see Cape Coral's 50 percent rule and the paperwork that decides it.
What this notice does not say
It gives no code section numbers — not for the Florida Building Code, not for ASCE 24-14, not for the Land Development Code. It does not define “recessed,” so there is no depth below which a shower pan stops counting. It does not define Lowest Floor Elevation, name a flood zone or a map, or say anything about lots outside a designated floodplain. It mentions no variance, waiver or alternative method.
And the detail most worth knowing: the notice says this “requirement has been in effect since December 2025 and is not a new policy or change in requirements.” That is the City's own characterisation. Read it carefully — a clarification issued in November 2026 saying the rule has applied since December 2025 is what a City publishes when enough people have been getting it wrong for long enough. If you have a set of plans drawn before December 2025 with a recessed shower in a flood zone, that is the sentence that should send you back to the drawings.
“New Required Inspection: Electrical Concrete-Encased Electrode (Ufer Ground)”
NOTICE TO INDUSTRY. Effective March 1, 2026. Printed date February 17, 2026, with the line “subject to change without notice.” No individual signs it; the Building Division is named in the body.
This one is a sequencing change, and sequencing changes are the ones that cost real money on a custom build.
A concrete-encased electrode — the trade calls it a Ufer ground — is a length of the foundation's reinforcing steel, or a conductor run inside the footing, used as the building's grounding electrode. It is cited in the notice to NFPA 70 (National Electrical Code), Section 250.52(A)(3), alongside the Florida Building Code Residential volume and Chapter 27 of the Building volume. No edition years are printed for any of them.
What changed on March 1, 2026 is that the City “will separate the Electrical Concrete-Encased Electrode inspection from the Slab inspection” — so the electrode is no longer signed off as part of the slab. The stated reason is to ensure the appropriate licensed professional performs the inspection.
The requirements, as printed:
The electrode is required where present and must be inspected while exposed and “before concrete is poured”.
The inspection happens “with the grounding electrode, reinforcing steel, or grounding conductor fully visible”.
“All connections, bonding, and continuity must be accessible at the time of inspection.”
It “must be scheduled through the standard inspection process” — it is not automatic and it is not bundled.
Then the sentence that makes this a notice and not a memo. Missing it “may result in required corrective action, including removal of concrete” or additional verification as the Building Official determines. And the escape hatch most builders would reach for is closed in advance: “Engineer letters will not automatically be accepted in lieu of a required inspection for concealed work.”
In practice that is one phone call between the concrete sub and the electrical sub on the morning of the pour. The notice says as much — it asks contractors to coordinate the two trades. Miss the call and the remedy is not paperwork.
What this notice does not say
It does not define “where present,” so when a concrete-encased electrode is deemed to exist is left to the field. It does not say who the “appropriate licensed professional” is. It does not name an inspection code or request line, give a turnaround time or a fee, or explain what the slab inspection covers now that the electrode has been pulled out of it. It says nothing about permits that already had their slab inspection before March 1, 2026 beyond the words “going forward.”
For how the City categorises failed inspections generally, and the documents that fail a request before anyone drives out, see why Cape Coral inspections fail.
“HB 803 – Clarification Regarding Minor Residential Work $7,500 Exemption Eligibility”
ADVISORY NOTICE TO INDUSTRY. Printed 06/26/2026. “Effective: 7/01/2026.” Signed “Regards, Shane Kittendorf, Building Official.”
Dated, signed, and it contradicts the thing most people believe about the statute it is about.
HB 803 is widely understood in this market to mean that residential work under $7,500 does not need a permit. The Building Official's notice says, in capitals of its own: “HB 803 does NOT create a blanket exemption from permitting requirements based solely upon project cost.”
The carve-out that follows probably swallows a large share of this city. “No exemption eligibility shall be considered for development located within a special flood hazard area” where a permit is otherwise required by the Florida Building Code, local floodplain management regulations, or National Flood Insurance Program requirements. Cape Coral is a coastal city built on canals. A great many lots here sit inside a special flood hazard area, and on those lots the cost test never gets reached.
Three more operative lines:
“Exemption eligibility is not automatic and remains subject to review and determination by the local enforcement agency” — the exemption is a request you submit through the City's portal, not a conclusion you reach yourself.
“Projects may not be artificially divided into multiple contracts, phases, invoices, or scopes of work” to evade permitting requirements or statutory thresholds.
“A local government has no legal duty to the owner, contractor, or successors or assigns thereof for exempted work” under Fs. 553.79(1)(g) — exempt work is uninspected work, and the notice says plainly who carries that.
The examples list is the most useful page in the document because it is absurdly specific, and specificity is what tells you where the line actually falls. Eligible for review, verbatim from the notice, includes “Interior and exterior painting”; “Baseboards, crown molding, and interior trim work”; “Additional blown insulation within existing attic spaces”; “Minor soffit repairs where overhangs are less than 12 inches and no structural framing modifications occur”; and “Replacement of flooring and tile, excluding shower pans, shower receptors, or wet-area waterproofing systems”.
Read that last one next to the shower-floor notice above and the City's thinking is visible: tile is cosmetic, the thing under the tile in a wet area is not.
Fences get a height test measured “from the bottom of the foundation to the top of the post”, under six feet, and only where the fence is not part of a pool safety barrier. Prefabricated storage units qualify only up to six feet in each of length, width and height, and only with no electrical, plumbing, mechanical or structural systems in them.
Work the notice says generally remains subject to permitting: electrical, plumbing, mechanical, gas, structural, roofing, pool construction, and Level 1 through 3 alterations.
What this notice does not say
It never defines how the $7,500 is measured. Not materials against total job cost, not labour plus materials, not per permit against per job against per year. The opening paragraph describes the statute as covering work “valued at less than $7,500 on the owner's property”, the FAQ adds that “The value of the work alone does not determine exemption review eligibility”, and the notice asks for documentation of the nature and value of the work. The measure itself is left open, and we are not going to supply a number the City declined to print.
Two other conditions worth knowing: the exemption is for single-family dwellings — the FAQ excludes condominiums and apartments — and if the property is held out for rent, lease or sale within one year, a licensed contractor must submit the request.
“Termite Certificate Inspection Process”
ADVISORY NOTICE. “Effective November 16, 2026.” No issue date, no signature, no contact — the newest of the four and the thinnest document of the four.
It is a process notice rather than a substantive one, but it is seven days old at the time of writing and it changes a step on every new build, addition and remodel that requires a Termite Certificate Inspection. Those requests now go through the City's CSS Portal.
Two sentences in it are worth having in front of you before you schedule anything.
“The date requested by the applicant is not a confirmed inspection date.” Staff review the request and the supporting documentation and set the actual date. If you have been treating a requested date as a booked date, stop.
And: “Inspection requests submitted without all applicable supporting documentation will be marked as FAILED.” Not held, not returned — failed, with a new request required afterwards. That is the same pattern the City applies elsewhere in its inspection process, and it is why the attachments matter as much as the timing.
What this notice does not say
It cites no code section, ordinance or statute, names no forms, and never lists what counts as “applicable supporting documentation.” It does not explain how a FAILED request is recorded or whether it can be corrected rather than refiled, does not say whether it reaches permits issued before November 16, 2026 or requests already in the queue, and carries no signature or issuing contact.
What the four have in common
Read together, a pattern emerges that is more useful than any one of them.
Three of the four are enforcement mechanics, not new standards. The shower-floor notice says it changes nothing. The electrode notice splits an existing inspection in two. The termite notice moves a request onto a portal. The rule was already there in each case; what changed is that it is now being checked separately, which in practice is the same as new.
Every one of them names a consequence and none of them names a remedy. Removal of concrete. Will not pass inspection. Marked as FAILED. There is no appeal path, no variance, no alternative-method clause anywhere in the four.
Three of the four are unsigned. Only the $7,500 notice carries a name. The other three are issued by “the Building Division,” with no individual accountable on the page and, in two cases, no issue date either.
The gaps are consistent and they are all definitional. What counts as recessed. Where an electrode is present. What the supporting documentation is. How the $7,500 is measured. In each case the City states the requirement and leaves the boundary to the field, which means the answer for your house comes from your plans examiner and your inspector, not from the document.
That last point is the honest summary of this entire series. A notice tells you what the City is going to look for. It does not tell you how the City will measure it on your lot. Anyone who quotes you one of these as a settled answer has read half of it.
The notices this site has already worked through
Four more from the same series have their own pages here, each built on the City's document rather than on a summary of it:
Change in Permit Requirements for Pool Safety Barriers, effective March 1, 2026 — the pool permit and the barrier permit were split, and the barrier needs its own document package, its own fees and its own Burrowing Owl Affidavit. See your pool permit does not include your pool cage.
GFCI Protection for Outdoor HVAC Equipment, effective September 1, 2026 — and the place where the City's advisory and Florida's own amendment do not line up. See GFCI on your outdoor AC unit.
Common Inspection Failures and Scheduling Expectations, April 2026 — the City's own taxonomy of why inspections fail, seven categories with the code section behind each. See why Cape Coral inspections fail.
Expired Permits, June 2025 — where the City's notice and the administrative chapter of the code give different numbers for the same deadline. See when a Cape Coral building permit expires.
The Burrowing Owl Affidavit named in the pool barrier notice is itself a document worth understanding before it holds up a permit — what Cape Coral requires before your permit sets out what the form asks and the buffers it sets.
And the largest open question in this subject is not in any notice. It is which edition of the Florida Building Code your permit will be reviewed under — see Florida's building code changes and what it means if you are building in Cape Coral.
Frequently asked questions
Where can I find Cape Coral's Notices to Industry?
On the City of Cape Coral website, under Departments, Development Services, Notices to Industry. The documents are grouped by year and each one is a PDF; the 2026 group held seventeen when we read it on November 23, 2026. There is no mailing list, no RSS feed and no announcement — the collection simply exists and is updated.
Is a Notice to Industry the same thing as a code requirement?
No. A notice is the Building Division telling the industry how it intends to apply a requirement that already exists, or announcing a change in process. Several carry the line “subject to change without notice.” None of them is adopted law. They are the best available indication of what plan review and inspection will actually do, which is a different and often more immediately useful thing.
Can I build a curbless shower in Cape Coral?
The City's November 2026 advisory does not prohibit a recessed shower floor. It says the recessed floor is part of the finished floor system and must itself meet Base Flood Elevation plus one foot when the Lowest Floor Elevation is determined, in new construction and in substantial improvements in designated floodplain areas. In practice that is a design problem solved on the drawings, by setting the floor system high enough that the recess still clears the required elevation — not a detail to discover at inspection. The notice gives no depth threshold below which a recess stops counting, so there is no published tolerance to work to.
What is a Ufer ground and why does it now need its own inspection?
It is a grounding electrode formed by the foundation itself — reinforcing steel, or a conductor run inside the footing — cited in the City's notice to Section 250.52(A)(3) of the National Electrical Code. Since March 1, 2026 Cape Coral inspects it separately from the slab, so that the appropriate licensed professional performs the inspection. It has to be inspected while exposed and before concrete is poured, with connections, bonding and continuity accessible.
What happens if the concrete goes down before the electrode inspection?
The notice says failure to schedule before concealment “may result in required corrective action, including removal of concrete” or additional verification as the Building Official determines, and that engineer letters will not automatically be accepted in place of a required inspection for concealed work. It does not define the circumstances in which removal would be required rather than verification.
Does HB 803 mean I do not need a permit for work under $7,500?
Not by itself. Cape Coral's Building Official published an advisory stating that HB 803 “does NOT create a blanket exemption from permitting requirements based solely upon project cost.” Exemption is a request submitted through the City's portal and subject to review, it does not apply where development sits in a special flood hazard area and a permit is otherwise required, and electrical, plumbing, mechanical, gas, structural, roofing and pool work generally remain permitted regardless. The notice also forbids splitting a project across contracts, phases or invoices to get under a threshold.
How is the $7,500 measured — materials, or the whole job?
The City's notice does not say. It describes the statute as covering work valued at less than $7,500 on the owner's property, states that the value of the work alone does not determine eligibility, and asks for documentation of the nature and value of the work. It never specifies materials against total cost, or per permit against per job against per year. Anyone giving you a confident answer on that point is not reading it off this document.
Does the $7,500 exemption apply to a new custom home?
No. The exemption is framed around minor residential work on an owner's existing property, and the examples are painting, trim, flooring, soffit repairs and similar. New construction is not in that category, and in any event the flood-hazard-area exclusion reaches most of the lots this market builds on.
Is a termite certificate inspection new?
The inspection is not new; the way you request it changed effective November 16, 2026. Requests for new construction, additions and remodels requiring a Termite Certificate Inspection go through the CSS Portal, a requested date is not a confirmed date, and a request submitted without all applicable supporting documentation is marked as FAILED and has to be resubmitted.
Do these notices apply to a house already under permit?
It varies by notice and most of them do not say clearly. The electrode notice applies to permits not yet issued or not yet through plan review where the inspection is required, plus everything issued “going forward.” The termite notice says nothing about requests already in the queue. The shower-floor advisory says it is not a change at all, which implies it reaches any plan still in review. This is the single most common question these documents fail to answer, and it is worth asking the Building Division directly about your own permit number rather than inferring it.
Should my builder be tracking these?
Yes, and the test of whether yours is tracking them is specific rather than general. Ask which notices from the current year affect your drawings and your inspection sequence, and ask to see the documents. A builder who follows this series will name them and send you the PDFs. A builder who does not will answer in generalities about staying current with code.
How we use these
We read this series as it publishes, because a notice is the earliest point at which a change becomes visible, and because the cost of catching one late is paid in built work rather than in paperwork. The shower-floor advisory is a drawing revision if you find it in design and a far more expensive problem if you find it at inspection. The electrode notice is a phone call if you know about it and a jackhammer if you do not.
Lux Development Group builds custom homes in Cape Coral and Lee County; our portfolio records six completed projects, which you can see at Lux Development Group projects in Cape Coral. Much of what we build sits on canal lots, where the flood-elevation half of this page is not an edge case but the ordinary condition — see waterfront custom homes in Cape Coral.
If you are planning a build or a major remodel here and want to know which of the City's current notices touch your drawings, call 239-580-6886 or email info@luxdevgroup.com. We will tell you which documents apply and send you the City's own paper rather than our summary of it.
Every quotation on this page is from a City of Cape Coral Notice to Industry or Advisory Notice published at capecoral.gov, read in full on November 23, 2026, and reproduced with the title and date printed on the document. The notices themselves state that they are subject to change without notice, and nothing here is a substitute for the Building Division's determination on your own permit.